Patel Engineering Limited
5,430words
14turns
0analyst exchanges
0executives
Key numbers — 40 extracted
rs,
INR 1,51,193
INR 51,027
0.2%
INR 6,840
13.40%
INR 2,945
21.6%
5.77%
101 Bps
INR 2.84
1.4%
Guidance — 20 items
REGD. OFFICE
opening
“Subansiri Hydropower Project – 4 out of 8 units now operational contributing 1,000 MW of clean energy to the national grid.”
REGD. OFFICE
opening
“CIDCO Water Tunnel Project – 812m tunneling works achieved in a single month (January 2026), setting a national benchmark across TBM tunneling.”
REGD. OFFICE
opening
“Investor Presentation 4 Key Ongoing Project Updates (1/2) Subansiri Hydropower Project Updates • • Project Value: INR 20,421 Mn.”
REGD. OFFICE
opening
“Competition status: 99% Kiru Hydropower Project Updates • Project Value: INR 23,258 Mn.”
Other Update
opening
“Kwar Hydropower Project Updates • Project Value: INR 24,610 Mn.”
Other Update
opening
“• Competition status: 37% Arun – III Hydropower Project Updates • Project Value: INR 14,348 Mn.”
Other Update
opening
“Achieved breakthroughs at key project elements including Main Access Tunnel (Power House) ; Dam Top Road Tunnel and Pressure Shaft 4 and Surge Gallery 2.”
Other Update
opening
“Recognition received from SAPDC for 29 million safe man-hours Shongtong Hydropower Project Updates • Project Value: INR 17,263 Mn.”
Other Update
opening
“• Competition status: 73% Parnai Hydropower Project Updates • Project Value: INR 4,740 Mn.”
Other Update
opening
“5 Key Ongoing Project Updates (2/2) Teesta VI Hydropower Project Updates • • Project Value: INR 14,462 Mn.”
Risks & concerns — 4 flagged
Achieved breakthroughs at key project elements including Main Access Tunnel (Power House) ; Dam Top Road Tunnel and Pressure Shaft 4 and Surge Gallery 2.
— Other Update
(Chemistry) from Women’s Christian College; over 20 years of experience in consulting across corporate strategy, process redesign, risk support management and compliance spanning banking & finance, manufacturing and services sectors.
— Other Update
• Capabilities to operate in geologically sensitive zones, high-altitude regions, and difficult rock formations.
— Other Update
• • Infra risk guarantee fund de-risks large-scale projects“ "Gati Shakti streamlines approvals & cuts turnaround times • Every INR 1 in infra generates INR 2.5- 3.5 in economic impact - ensuring sustained government backing.
— Other Update
Speaking time
12
1
1
Opening remarks
REGD. OFFICE
Patel Estate Road, Jogeshwari (W), Mumbai – 400 102. India Phone +91 22 26767500, 26782916 Fax +91 22 26782455, 26781505 Email headoffice@pateleng.com Website: www.pateleng.com Patel Engineering Limited INVESTOR PRESENTATION April, 2026 INVESTOR PRESENTATION May 2026 Snapshot 75 + Years of Industry Presence 350+ Projects Executed INR 1,51,193 Mn Total Order Book 87+ Dams Constructed 300+ KM Tunnels 53 Ongoing Projects 2.96 Book-to-Bill (FY26) 14 States – Domestic Presence 2 Nepal & Bhutan – International Presence 15,000+ MW Hydro Project 5.5+ Lakh Acres Irrigated 1,200+ KM of Roads Developed Investor Presentation 2 Q4-FY26 / FY26 PERFORMANCE Key Financials and Operational Highlights FY26 Consolidated Performance FY26 – Key Highlights Revenue from Operations INR 51,027 Mn 0.2% YoY EBITDA EBITDA Margin INR 6,840 Mn (6.7)% YoY 13.40% (100) Bps YoY PAT INR 2,945 Mn 21.6% YoY PAT Margin 5.77% 101 Bps YoY Diluted EPS INR 2.84 /Share 1.4% YoY Q4-FY26 Consolidated Performance Revenue from Oper
Other Update
4 out of 8 units commissioned supplying 1000 MW of clean energy to the grid. Civil works up to unit 6 completed.
Other Update
Over 11,50,000 cubic meters of dam concreting completed. Unit 3 and 4 of Power Intake structure completed. Power house units 1, 2 and 3 completed. Kwar Hydropower Project Updates • Project Value: INR 24,610 Mn. • Competition status: 37% Arun – III Hydropower Project Updates • Project Value: INR 14,348 Mn. • Competition status: 98%
Other Update
Over 3,00,000 cubic meters of dam concreting completed. Achieved breakthroughs at key project elements including Main Access Tunnel (Power House) ; Dam Top Road Tunnel and Pressure Shaft 4 and Surge Gallery 2.
Other Update
Unit 1, 2, and 3 Machine Hall Slab completed. Head Race Tunnel works completed. Recognition received from SAPDC for 29 million safe man-hours Shongtong Hydropower Project Updates • Project Value: INR 17,263 Mn. • Competition status: 73% Parnai Hydropower Project Updates • Project Value: INR 4,740 Mn. • Competition status: 60%
Other Update
Over 1,50,000 cubic meters dam concreting completed. All civil works for the 3 powerhouse units completed. Surge shaft lining works completed. Investor Presentation