PNC Infratech Limited
7,830words
261turns
19analyst exchanges
4executives
Management on call
Yogesh Kumar Jain
MANAGING DIRECTOR, PNC INFRATECH LIMITED
T. R. Rao
DIRECTOR, INFRA - PNC INFRATECH LIMITED
Bhupinder Sawhney
Infratech Limited
Mr. D. K. Maheshwari
VICE PRESIDENT FINANCE, PNC INFRATECH LIMITED
Shravan Shah
DOLAT CAPITAL
Key numbers — 40 extracted
20%
40%
10%
Rs. 37 Crore
35%
Rs.
24,590 crore
Rs.
2390 crore
Rs. 1029 crore
Rs. 20,000 crore
Rs 7,439 Crore
61%
39%
Advertisement
Guidance — 20 items
Shravan Shah
opening
“As a reminder, all participant lines will be in the listen only mode and there will be an opportunity for you to ask questions after the presentation concludes.”
Yogesh Kumar Jain
opening
“First, I will share my thoughts on a few sectoral highlights which will be followed by financial and operational highlights of the Company.”
Yogesh Kumar Jain
opening
“In such case, 20% of bid project cost would only be paid during construction, compared to current norm of 40%.”
Yogesh Kumar Jain
opening
“NHAI is planning to award around 10% of projects on BOT-Toll mode, from its target of 6,500 kilometers in the current fiscal, with certain modifications in the contract conditions.”
Yogesh Kumar Jain
opening
“Concession agreement for the remaining project, four laning of Sonauli - Gorakhpur will be signed shortly.”
Yogesh Kumar Jain
opening
“We will keep you updated on the same, going forward.”
Yogesh Kumar Jain
opening
“1029 crores till June 2022 and the balance will be invested over the next 2-3 years.”
Shravan Shah
qa
“Sir, if you speak the disclaimer that will be better from your side.”
T. R. Rao
qa
“like you onboard for this, would your aggression in bidding going forward, would it be the same given how the equity outflow would be higher from our side?”
T. R. Rao
qa
“So we should able to fund those kind of equity requirements, even if NHAI goes for the 20% kind of amount, because earlier also we bid for a conventional annuity project wherein we used to put 100% of our entire funding from our side.”
Risks & concerns — 4 flagged
As mentioned in the previous earnings calls, company continues to look for a calibrated diversification to maintain the growth momentum, without assuming the concentration risk.
— Yogesh Kumar Jain
Since we have 5-months’ time post signing of the agreement, both sides what we expect the sufficient length of land will be available at the time of declaration of appointed date and we don’t foresee a major concern in that.
— T. R. Rao
So good margins have improved in this quarter, but last Q4 there was margin compression given that the import inflation is easing can we expect to go back to 14% margin for the fiscal?
— Mohit Kumar
We are bidding in the same area where all we are working in UP and it is not a difficult work that we are having an issue.
— Yogesh Kumar Jain
Advertisement
Q&A — 19 exchanges
Speaking time
44
42
36
28
20
17
12
12
9
8
Advertisement
Opening remarks
Shravan Shah
Ladies and gentlemen, good day and welcome to the PNC Infratech Limited Q1 FY23 Earnings Conference Call hosted by Dolat Capital. As a reminder, all participant lines will be in the listen only mode and there will be an opportunity for you to ask questions after the presentation concludes. Should you need assistance during the Conference Call, please signal an operator by pressing “*,” then “0” on your touch tone phone. Please note that this conference is being recorded. I now hand the conference over to Mr. Shravan Shah from Dolat Capital. Thank you and over to you, sir. Thank you, good afternoon, everyone. I would like to welcome you all for Q1 FY23 results Conference Call of PNC Infratech Limited. We thank the management for giving us the opportunity to host the call. We have senior management team of PNC Infratech with us. I congratulate the entire team of PNC Infratech for robust performance in Q1 FY23, without wasting much time. I would now hand over the floor to Yogesh sir for o
Yogesh Kumar Jain
Good afternoon, everyone and a very warm welcome to all of you present on the call, to discuss our financial results for Q1FY23. Today along with me, I have Mr. T.R. Rao, Director (Infra), Dr. Bupinder Sawhney, Chief Financial Officer and Mr. D. K. Maheshwari, Vice President (Finance) and Strategic Growth Advisors - our Investor Relations Advisors. First, I will share my thoughts on a few sectoral highlights which will be followed by financial and operational highlights of the Company. The pace of highway construction in Q1 of FY23 in the country slowed down and stood at 22 km a day compared to 25 km a day on Year-on-Year basis due to higher input costs and early onset of monsoon in some parts of the country. Ongoing active monsoon across the country, continuous rains, and flood like situations in some parts, expected to affect pace of construction in the first half of Q2 of FY23. MoRTH and NHAI contemplating to reduce the upfront payment by half ,in HAM projects. In such case, 20% of
Standalone Quarterly Result
Revenue of 1st quarter of FY23 is Rs. 1,758 crore which is higher by 41% as compared to Rs. 1,251 crore in 1st quarter of FY22. The EBITDA for the 1st quarter is RS. 258 crore which is higher by 47% as compared to Rs. 175 crore in Q1 of FY22. The EBITDA margin for the 1st quarter of FY23 is 14.7%. The PAT for the 1ST quarter of FY23 is Rs. 167 crore as compared to Rs. 93 crore in the 1st quarter of FY22, a growth of 79% on YoY basis. Consolidated Financials for the quarter ended 30thJune 2022. Consolidated revenue of 1ST quarter of FY23 is Rs. 2,053 crore as compared to Rs. 1,463 crore in Q1 of FY22, growth of 40%. PNC Infratech Limited August 10, 2022 The consolidated EBITDA for the 1st quarter of FY23 is Rs. 518 crore which higher by 43% as compared to Rs. 363 crore for the 1st quarter of the corresponding quarter last year. The EBITDA margin for Q1 FY23 is 25.2%. The consolidated PAT for Q1 FY23 is RS. 241 crore as compared to Rs. 118 crore in Q1 FY22, a growth of 104%. ON THE STAND
Advertisement