Bharat Heavy Electricals Limited
934words
0turns
0analyst exchanges
0executives
Key numbers — 14 extracted
5.5%
pent‐up household spending and discretionary expenditure Industrial activity (IIP index) grew by 5.5% during Apr‐Nov 2022 period Core sectors of economy like cement, steel, refinery etc and rail tra
9.8%
eaked in India and abroad, central banks easing policy rate hikes Electricity generation grew at 9.8% during Apr‐Nov 2022‐23 period to meet the rising power demand Domestic economy advancing steadil
6.3%
ing Apr‐Nov 2022‐23 period to meet the rising power demand Domestic economy advancing steadily – 6.3% GDP growth in Q2FY23, NSO projecting GDP growth rate of 7.0% for FY23 Impetus on energy security
7.0%
Domestic economy advancing steadily – 6.3% GDP growth in Q2FY23, NSO projecting GDP growth rate of 7.0% for FY23 Impetus on energy security due to adverse geopolitical scenario, rising power demand co
13%
Exports Total 12,826 4,757 256 17,839 86,127 13,009 4,558 1,03,694 Industry, 13,009 , 13% Exports, 4,558 , 4% In Rs. Crore Power Industry Exports Power, 86,127 , 83% 5 Order Book
4%
6 4,757 256 17,839 86,127 13,009 4,558 1,03,694 Industry, 13,009 , 13% Exports, 4,558 , 4% In Rs. Crore Power Industry Exports Power, 86,127 , 83% 5 Order Book Prominent orders rec
83%
ry, 13,009 , 13% Exports, 4,558 , 4% In Rs. Crore Power Industry Exports Power, 86,127 , 83% 5 Order Book Prominent orders received in Q3FY23 include: Supply of TG Rotor for thermal powe
65 MW
0 kV GIS Substation and 400 kV bay extension on turnkey basis Supply and supervision of E&C of 4x65 MW STG, 1x45 MW STG from various industrial captive power plants Supply of Motor driven (VFD fed)
45 MW
tation and 400 kV bay extension on turnkey basis Supply and supervision of E&C of 4x65 MW STG, 1x45 MW STG from various industrial captive power plants Supply of Motor driven (VFD fed) Recycle Gas C
660 MW
3, focus on project delivery led to: Synchronization and achievement of full load of Unit#1 of 3x660 MW North Karanpura Thermal Power Project of NTPC Ltd Synchronization of 14.9 MW BPTG of Tata Chemi
14.9 MW
load of Unit#1 of 3x660 MW North Karanpura Thermal Power Project of NTPC Ltd Synchronization of 14.9 MW BPTG of Tata Chemicals Ltd., Mithapur, Gujarat Synchronization of 18.5 MW STG of Gujarat Heavy
18.5 MW
Synchronization of 14.9 MW BPTG of Tata Chemicals Ltd., Mithapur, Gujarat Synchronization of 18.5 MW STG of Gujarat Heavy Chemicals Ltd. (GHCL) Synchronization of 45 MW STG of Grasim Vilayat, Gujar
Advertisement