I February 08, 2023 BSE Limited National Stock Exchange of India Limited Phiroze Jeejeebhoy Towers, Exchange Plaza, C-1, Block-G, Dalal Street, Mumbai- 400 001 Bandra Kurla Complex, Bandra (East),
100%
y 20 Years of execution 18 Active Projects 10 HAM Projects Pan India Presence (Incorporation) 100% India 9 States North 57% South 24% East 16% West 3% StrongGrowth Trajectory RobustBusinessModel
57%
Active Projects 10 HAM Projects Pan India Presence (Incorporation) 100% India 9 States North 57% South 24% East 16% West 3% StrongGrowth Trajectory RobustBusinessModel 27% Revenue CAGR (4 years
24%
ojects 10 HAM Projects Pan India Presence (Incorporation) 100% India 9 States North 57% South 24% East 16% West 3% StrongGrowth Trajectory RobustBusinessModel 27% Revenue CAGR (4 years) 29% EBI
16%
0 HAM Projects Pan India Presence (Incorporation) 100% India 9 States North 57% South 24% East 16% West 3% StrongGrowth Trajectory RobustBusinessModel 27% Revenue CAGR (4 years) 29% EBITDA CAGR
3%
jects Pan India Presence (Incorporation) 100% India 9 States North 57% South 24% East 16% West 3% StrongGrowth Trajectory RobustBusinessModel 27% Revenue CAGR (4 years) 29% EBITDA CAGR (4 years
27%
ndia 9 States North 57% South 24% East 16% West 3% StrongGrowth Trajectory RobustBusinessModel 27% Revenue CAGR (4 years) 29% EBITDA CAGR (4 years) 42% Profit CAGR (4 years) 2100+ Fleet of Modern
29%
uth 24% East 16% West 3% StrongGrowth Trajectory RobustBusinessModel 27% Revenue CAGR (4 years) 29% EBITDA CAGR (4 years) 42% Profit CAGR (4 years) 2100+ Fleet of Modern Equipment Multiple Digita
42%
trongGrowth Trajectory RobustBusinessModel 27% Revenue CAGR (4 years) 29% EBITDA CAGR (4 years) 42% Profit CAGR (4 years) 2100+ Fleet of Modern Equipment Multiple Digital initiatives to enhance p
23%
l h g i H s h t n o M e n N i Revenue EBITDA & EBITDA Margin (%) PAT & PAT Margin (%) 9,224 23% 11,312 16.5% 1,521 24% 16.7% 1,893 9.6% 9.8% 889 25% 1114 Q3FY22 Q3FY23 Q3FY22 Q3FY2
16.5%
h t n o M e n N i Revenue EBITDA & EBITDA Margin (%) PAT & PAT Margin (%) 9,224 23% 11,312 16.5% 1,521 24% 16.7% 1,893 9.6% 9.8% 889 25% 1114 Q3FY22 Q3FY23 Q3FY22 Q3FY23 Q3FY22 Q3FY
16.7%
Revenue EBITDA & EBITDA Margin (%) PAT & PAT Margin (%) 9,224 23% 11,312 16.5% 1,521 24% 16.7% 1,893 9.6% 9.8% 889 25% 1114 Q3FY22 Q3FY23 Q3FY22 Q3FY23 Q3FY22 Q3FY23 25,893 14% 29
Guidance — 2 items
Project type break-up
opening
foray into HAM to tap the growing opportunity EPC 61% Other Projects update during 9MFY23 Project Awarded Details of LOA issued after 01.04.2022 S.
Project type break-up
opening
1 Project Name Construction of 6 - Lane Greenfield Karnal Ring Rd starting from NH44 near Vill Shamgarh ( Design Km 0+00) and terminating at Karnal Munak Road (MDRI115) Vill Samalakhal (Design km 34.5 ) under Bharatmala Pariyojna in the satate of Haryana on Hybrid Annuity Mode Karnal Ring road LOA issued on 29.12.2022 S.
Advertisement
Speaking time
Client type break-up
1
Geographical break-up
1
Project type break-up
1
Company Contact
1
Investor Relations Contact
1
Opening remarks
Geographical break-up
successful diversification in various states AP, 6% Delhi, 10% Karnataka, 7% Rajasthan, 2% Haryana, 8% UP, 39% Telangana, 11% Odisha, 16% Maharashtra, 1% HAM 39%
Project type break-up
foray into HAM to tap the growing opportunity EPC 61% Other Projects update during 9MFY23 Project Awarded Details of LOA issued after 01.04.2022 S. No. 1 Project Name Construction of 6 - Lane Greenfield Karnal Ring Rd starting from NH44 near Vill Shamgarh ( Design Km 0+00) and terminating at Karnal Munak Road (MDRI115) Vill Samalakhal (Design km 34.5 ) under Bharatmala Pariyojna in the satate of Haryana on Hybrid Annuity Mode Karnal Ring road LOA issued on 29.12.2022 S. No. Project Name 2. Declaration of appointed date between 1.10.2022 to 31.12.2022 1 2 Execution of Civil & Associated works on Engineering Procurement & Construction (EPC) basis of Development of an Access- Controlled Six lane (Expandable to Eight lane) Greenfield ‘Ganga Expressway’[Group-II, from Km. 137+600 (Village: Nagla Barah, Distt: Budaun) to Km. 289+300, (Village: Ubariya Khurd, Distt: Hardoi), Design length=151.700 Km] in the State of Uttar Pradesh on DBFOT (Toll) basis under PPP- GANGA EXPRESSWAY Construction
Company Contact
Rajeev Mishra (CFO) rajeev.mishra@hginfra.com III Floor, Sheel Mohar Plaza, A-1, Tilak Marg, C-Scheme, Jaipur - 302001
Investor Relations Contact
Sana Kapoor Go India Advisors sana@GoIndiaAdvisors.com M:+91 81465 50469 Priya Sen Go India Advisors priya@GoIndiaAdvisors.com M:+91 8334841047 Sheetal Khanduja Go India Advisors sheetal@GoIndiaAdvisors.com M:+91 97693 64166 HG Infra Board Presentation – Q3 & 9MFY23
Advertisement
← All transcriptsHGINFRA stock page →