Petronet LNG Limited
11,384words
0turns
0analyst exchanges
0executives
Key numbers — 40 extracted
rs,
sification terminal and presently it is running almost at its full capacity. During the last 17 years, consecutive years PLL has been paying the dividend to all its shareholders. I would like to highlig
Rs. 20,685 crore
ts meeting as on 30th October 2023 has approved investment in petrochemical project with a cost of Rs. 20,685 crores. The project consists of PDH, that is propane dehydrogenation to produce the propylene of 750 KTP
20,685 crore
think these are the general in nature and we have already shared that the total project cost is of 20,685 crores, which includes all the soft costs like IDC, escalation, contingency, margin money, everything ha
16%
ny projects which is set by our board and it envisages to get better than the company benchmark of 16% of equity IRR. Availability of cash reserve with the company will meet our equity obligation. Our
10%
We established that by the time our project is completed, we will be able to meet maybe less than 10% of demand supply gap and still there will be a scope for many PP plant to come in the country. The
, crore
e quantum of synergies that you see between the LNG and the Petchem? I mean in amount terms, rupees, crore terms, if you could just highlight and where do they come from? Mr. A. K. Singh, MD & CEO: So, a
50 crore
ct is what I wanted to check. And also, if you would quantify it in rupees, crore terms, let's say 50 crores will come from this area or 100 crores will come from this area and the operating cost savings pa
100 crore
, if you would quantify it in rupees, crore terms, let's say 50 crores will come from this area or 100 crores will come from this area and the operating cost savings part, just like that I meant. Mr. A. K.
21,000 crore
please forgive me if the calculations seem too simplistic. Our understanding is that if I look at 21,000 crores of investment, very simplistically to make a 14% pre-tax ROC, you need to basically make on a 0.7
14%
Our understanding is that if I look at 21,000 crores of investment, very simplistically to make a 14% pre-tax ROC, you need to basically make on a 0.75 million ton of sales volume, which is the capaci
0.75 million
ores of investment, very simplistically to make a 14% pre-tax ROC, you need to basically make on a 0.75 million ton of sales volume, which is the capacity of the plant. Somewhere around $650 a ton of EBITDA is
20,000 crore
ere the EBITDA breakeven is in terms of per ton. Mr. A. K. Singh, MD & CEO: See, when I say this 20,000 crore is the total project cost, what does it include, I already mentioned to you. When we execute the p