G R Infraprojects Limited
8,569words
204turns
12analyst exchanges
1executives
Management on call
Parikshit Kandpal
HDFC SECURITIES
Key numbers — 40 extracted
INR1,234 crore
INR1,128 crore
9.76%
10.39%
INR262 crore
INR3,136 crore
INR246 crore
INR4,300 crore
INR21,000 crore
INR3,700 crore
INR6 lakh crore
INR1.25 lakh crore
Advertisement
Guidance — 20 items
Ajendra Agarwal
opening
“The company has won one power transmission and distribution project of INR3,136 crores and one highway project of INR246 crores.”
Ajendra Agarwal
opening
“As on the date, one DBFOT project of INR3,700 crores appointment date is awaiting and – of INR4,300 crores approximately, which are to be opened.”
Ajendra Agarwal
opening
“It has taken a big leap now and from this year onwards, roughly 3-gigawatts of PSP will be added on average every year as per the Central Electricity Authority.”
Ajendra Agarwal
opening
“By 2032, the target is somewhere around 50 gigawatt capacity coming from the hydro-pumped storage.”
Anand Rathi
opening
“Balance promoter contribution required to be made for our operational or under construction HAM BOT or power transmission project is INR3,205 crores, which we are expecting contribution of almost INR500 crores in the second half of the fiscal 2026.”
Shravan Shah
qa
“Sir, first, a couple of questions on the guidance and then maybe have a detail on that.”
Ajendra Agarwal
qa
“We will grow 5-10% in the revenue in the second half.”
Ajendra Agarwal
qa
“Shravan bhai, so that guidance in terms of inflow for the current year remains the same what we have given in the past.”
Ajendra Agarwal
qa
“Now the issue is only thing is that project awarding or bidding is getting delayed.”
Ajendra Agarwal
qa
“What we are targeting for the current year, what we have target INR20,000 to INR25,000 crores new project we will try to win.”
Risks & concerns — 7 flagged
If you look at our planning now, then the biggest challenge for us is the highway.
— Ajendra Agarwal
Because even in this year, what we are expecting is that in the current year, we will not de-grow.
— Ajendra Agarwal
Even if we consider the current backlog, if those orders also receive the appointed, then also 15% should not be a challenge.
— Vaibhav Shah
So, yes, there is a possibility of Chandrapur, but even Pune Ring Road E6 can be cancelled due to this challenge on technical grounds?
— Vaibhav Shah
So, it is very difficult as of now to tell about that what kind of order we will be getting in next year.
— Ajendra Agarwal
But there is a network and technical criteria we can say that after the bidding starts 50% people will be able to stay but who will be able to stay who will be able to participate, it is difficult to say.
— Anand Rathi
And this last one question to Ajendra ji on a broader infra theme, so sir last two years we have seen a slowdown in the sector, now Government's focus is on GST cuts along with consumption and the pipelines which are being pushed out, especially on the NHI which has been one of the large ordering segment.
— Parikshit
Advertisement
Q&A — 12 exchanges
Speaking time
76
21
16
15
15
14
12
9
9
5
Advertisement
Opening remarks
Parikshit Kandpal
Thank you, Rashi. Without taking further time, I’ll now hand the floor to Ajendra ji for his opening remarks on the industry and the financial updates. Thank you, and over to you, sir.
Ajendra Agarwal
Thank you, Mr. Parikshitji. Dear all, a very good afternoon. I welcome you all to earning call of GR Infraprojects Limited for Q2 Financial Year ’26. I also have with us on call Mr. Anand Rathi, the CFO, and Mr. Ankit Maheshwari, the Deputy CFO of the company. First, let me provide the key highlights on our Q2 performance, followed by recent developments in the infrastructure sector, followed by question-and-answer session. Revenue from operation in second quarter of fiscal 2026 stood at INR1,234 crores as against INR1,128 crores in the corresponding period in previous financial year. The EBITDA margin excluding other income for the current quarter stood at 9.76%, as against 10.39% in the corresponding period in previous financial year. During the quarter, the company has repaid the debt of INR262 crores, which has resulted in improved debt-equity ratio of 0.03, one of the best in the sector. The company has won one power transmission and distribution project of INR3,136 crores and one
Anand Rathi
Good afternoon. Thank you, sir. The key highlights of the quarter two performance of the company. Our standalone revenue from operation was INR1,234 crores approximately in quarter ended September 2025, which is increased by 9.36% year-on-year basis. This was primarily on account of the higher execution of the projects. Our consolidated revenue from the operation was INR1,602 crores in quarter ended September 2025, which is increased by almost 15% year-on-year basis compared to INR1,394 crores in quarter ended September 2024. Our stand-alone EBITDA margins stood at 9.76% in quarter ended September 2025 from 10.39% in quarter ended September 2024. This decrease is primarily due to one-time claim income recognized of INR21 crores in quarter ended September 2024. Consequently, our EBITDA margin at gross level also has margin decreased to 24% in quarter ended September 2025 from 25% quarter ended September 2024. Profit after tax at stand-alone level increased to INR131 crores in quarter en
Advertisement