Adani Green Energy Limited
4,462words
9turns
0analyst exchanges
0executives
Key numbers — 40 extracted
rs,
5,290 MW
2,220 MW
2,048 MW
172 MW
rs
35
100%
0.9%
1.9%
0.4%
5.2%
5,290
MW
Guidance — 6 items
Financing
opening
“Highest rated renewable issue from India at BB+ Refinanced 648MW Kamuthi Solar Power project from PFC ~80% of operational portfolio refinanced”
New commissioning
opening
“ 50 MW Solar Power Project at Jhansi, UP in May’19 100 MW of 200 MW Solar Power Project at Rawara, Rajasthan in August’19 100 MW OEM Wind Power Project at Gujarat in July’19”
Two New Bids Won
opening
“ 130 MW Wind Project by SECI at Rs 2.83/kWh 600 MW Wind-Solar Hybrid Project by SECI at Rs 2.69/kWh Total portfolio of 5,290MW 8 Recent Industry Developments Power Sector Policy Reforms Ministry of Power mandates DISCOMs to open and maintain adequate LC as payment security mechanism under PPA.”
Two New Bids Won
opening
“ Despatch to DISCOM will be scheduled after written confirmation by generators with regards to opening of LC by DISCOMs.”
Two New Bids Won
opening
“Estimated Quarterly CUF for 1.9 GWAC Portfolio Target CUF 28.00% 26.00% 24.00% 22.00% 20.00% 25.55% 25.31% Actual 21.44% 23.59% 27.54% Q1 FY20 Q2 FY20 Q3 FY20 Q4 FY20 Annual CUF Target for existing solar capacity of 1948 MW is ~24.5% 13 Note: P50 targets based on internal estimates AGEL solar portfolio operating near P50 levels 03.”
Notes
opening
“Additionally, for SECI projects, corpus fund covering 3 months is provided @ AGEL is in the process of acquiring beneficial interest in the project, subject to the terms of the PPA 26 Restricted Group-1 STRICTLY CONFIDENTIAL STRICTLY CONFIDENTIAL 930 MW Solar Portfolio Bridge : RG-1 Actual vs.”
Advertisement
Speaking time
2
1
1
1
1
1
1
1
Opening remarks
Solar
Near P50 performance achieved for the portfolio @ 25.3% CUF Plant availability at 99.5% Grid availability at 98.7% 20 MW solar plant at Kanasar, Rajasthan conferred with Leadership In Performance award by CII
Wind
Plant availability at 86.8% 100% Grid availability AGEL’s first Wind plant at Kutch, Gujarat achieved CUF of 65.5% vs. est. 50.1%
Performance
Revenue from Sale of Energy of Rs. 554 Cr, up 17% EBITDA of Rs. 496 crore, up 13% EBITDA Margin of 90% Cash Profit of Rs. 257 crore
Financing
USD 500 mn, 5yr Green Bond issued. Highest rated renewable issue from India at BB+ Refinanced 648MW Kamuthi Solar Power project from PFC ~80% of operational portfolio refinanced
New commissioning
50 MW Solar Power Project at Jhansi, UP in May’19 100 MW of 200 MW Solar Power Project at Rawara, Rajasthan in August’19 100 MW OEM Wind Power Project at Gujarat in July’19
Two New Bids Won
130 MW Wind Project by SECI at Rs 2.83/kWh 600 MW Wind-Solar Hybrid Project by SECI at Rs 2.69/kWh Total portfolio of 5,290MW 8 Recent Industry Developments Power Sector Policy Reforms Ministry of Power mandates DISCOMs to open and maintain adequate LC as payment security mechanism under PPA. Despatch to DISCOM will be scheduled after written confirmation by generators with regards to opening of LC by DISCOMs. In case LC is not opened by DISCOM, resulting in non-scheduling of power, the DISCOM is liable to pay the fixed charges to the generator. MNRE has clarified that fixed charges for Solar, Wind & small Hydro will be PPA tariff as signed by DISCOMs Renewable Sector Reforms and Developments Amendment in Wind Guidelines allowing • 100% Possession of land till Commissioning instead of 7 months from PPA • Revision in CUF allowed once in 3 years from COD • Full tariff on power injected before Schedule Commissioning Date MoP has granted regulatory approval for 66.5 GW of
Advertisement